The term “well-planned is half done” is true also in construction. If you need help in advancing the construction project, please contact our company. We will gladly advise you on how to build with concrete sustainably and with high quality.
The scheduling of the construction phases should be done carefully and should start after the architectural drawings from building design so that all the drawings are largely finished already in the tender stage. We can also offer a complete package for precast element design. The drawings for the electrical and HVAC plans should also to be completed no later than when the construction materials are ordered. In precast concrete construction, it is particularly important to know the elements of the design elements of the production structure. The measurement of sockets, piping, apertures and reserves must be carefully planned prior to the movement to production of the elements in order to avoid chiseling and diamond sawing finished precast elements on site.
The installation of precast concrete installation requires careful foundation work to be done, a crane and a qualified crew for the installation of the elements. Both cost savings and maintaining the schedule are achieved through the efforts of the entire organization and advanced planning in building.
In your planning, deliveries with free access to the construction site with a heavy full trailer must be taken into account. Particularly for the plots on hills, the necessary space and free access both for cranes and cars carrying the precast elements must be carefully considered for the installation. The heaviest and largest element defines the necessary size of the crane and sets the requirements for the transport.
When performing precast element planning, the weight and height of the element must be taken into consideration as the size of the elements may cause problems when moving the elements on public roads when going underneath bridges and power lines. High loads or oversized units require special transport permits and sometimes even traffic control.
The necessary permits for construction must definitely be ready when the construction project is initiated.
When you design private homes using concrete, the availability of the precast elements is best insured by ordering the elements in the winter months for the next summer because transfer of the individual element production amidst larger construction projects and well as on a hectic schedule is difficult.
Element design
Element design after the blueprints must be made well in advance so that the production of the precast concrete can be scheduled in accordance with the desired delivery date. Structural design takes time and too often hastily made plans cause problems both in bid calculation and production, as well as on the construction site.
The installation of precast concrete
Professional and leading industry experts on safe installation should be used for the installation of precast elements. You can get additional information from our company.